Installation guidelines
Installation guidelines
Please select one or more chapters to download.
Table of contents

Installation direction and fastening

The roof shingles are laid from right to left and should be laid in rows (in horizontal rows). The offset from row to row is 1/3 - see “V” marking on the upper fold of the shingles.

Each shingle is fastened with a clip and a supplied 2.8/25 grooved nail (= base attachment).

In areas particularly prone to storms, a wind load calculation is required and fastenings must be adjusted according to the calculation.

1 Head
2 Chest
3 Heel
4 Foot
5 Back
ST Snow guard
V Offset
H Clip