Preparations for installation

When installing FX12 facade panels no vertical seam must lie on top of each other, a lateral offset of 220 mm has to maintained. When combining large and small FX.12 panels, the joint of the first panel must be started in area “X” for each new row.

After an opening (window, doors, etc.), the joint of the first panel must be at a multiple of 700 mm from the joint of the last one placed before the opening.

Note

The panel spacing must be transferred for the starting row. For each additional row, it is sufficient to maintain the joint offset after opening.